ExxonMobil Tank T27 GRP Removal

Results

Five crew on RPR induction finished in eight days what chipping hammers would have taken up to 30 people more than 15 days to do.
Days to complete
0 Days
Crew, not 30
0 Crew
GRP thickness removed (up to)
0 mm

Solution

RPR induction removed 5 to 16 mm GRP far faster than chipping hammers, with 5 crew instead of 30.

MFL floor scanning ran alongside removal, so inspection and trades kept working in the vessel.

Project Overview

ExxonMobil’s Jurong Island tank farm in Singapore is a major hazard facility, and Tank T27 is a high-capacity crude oil storage tank. Its annular was lined with glass reinforced plastic (GRP) 5 to 16 mm thick.

  • Location: Jurong Island, Singapore
  • Asset: Tank T27, high-capacity crude oil storage tank
  • Coating: GRP lining on the annular, 5 to 16 mm thick
  • Conventional method: chipping hammers remove less than 1 m per man per day
  • Site constraint: 30-person limit in the vessel, capping progress at under 20 m a day without a properly clean surface
  • Conventional program: 15+ days

Services Included

ACR Tech travelled to Singapore and removed the GRP with RPR induction instead of chipping hammers.

  • RPR induction removal of thick GRP from the tank annular
  • Surface preparation leaving a cleaner surface, easier to blast
  • Works carried out alongside MFL floor scanning so inspection kept running
  • Reduced crew footprint inside the vessel, with 5 crew instead of 30

Conclusion

Five crew on RPR induction finished in eight days what chipping hammers would have taken up to 30 people more than 15 days to do, leaving a cleaner surface ready for blasting.

  • Completed in 8 days against a 15+ day conventional program
  • Done with 5 crew instead of 30
  • Removal far faster than other methods
  • MFL floor scanning and trades kept working in the vessel
  • ExxonMobil has since continued to engage ACR Tech on other projects

Project Overview

26 June to 4 July

ExxonMobil’s Jurong Island tank farm in Singapore is a major hazard facility, and Tank T27 is a high-capacity crude oil storage tank. Its annular was lined with glass reinforced plastic (GRP) 5 to 16 mm thick.

  • Location: Jurong Island, Singapore
  • Asset: Tank T27, high-capacity crude oil storage tank
  • Coating: GRP lining on the annular, 5 to 16 mm thick
  • Conventional method: chipping hammers remove less than 1 m per man per day
  • Site constraint: 30-person limit in the vessel, capping progress at under 20 m a day without a properly clean surface
  • Conventional program: 15+ days

Services Included

ACR Tech travelled to Singapore and removed the GRP with RPR induction instead of chipping hammers.

  • RPR induction removal of thick GRP from the tank annular
  • Surface preparation leaving a cleaner surface, easier to blast
  • Works carried out alongside MFL floor scanning so inspection kept running
  • Reduced crew footprint inside the vessel, with 5 crew instead of 30

Conclusion

Five crew on RPR induction finished in eight days what chipping hammers would have taken up to 30 people more than 15 days to do, leaving a cleaner surface ready for blasting.

  • Completed in 8 days against a 15+ day conventional program
  • Done with 5 crew instead of 30
  • Removal far faster than other methods
  • MFL floor scanning and trades kept working in the vessel
  • ExxonMobil has since continued to engage ACR Tech on other projects