Case Study

Project: Isaac Plain Sump Refurbishment


Completed by:
ACR Technologies
client:
IMATECH
Location:
Moranbah, Queensland
Dates:
31st October – 9th November
Sump Specifications
Diameter ranges:
2m – 5m
Height Ranges:
3m – 7m
Coating Thickness:
> 2000 microns
Project details
Removal of Polyurea coating from 7 sumps varying in sizes.
Equipment
  • 1 x RPR induction unit
  • 1x Water Cooling unit
  • 1x 100kva Generator 
Personnel
4 x crew members
(2 people on each shift, 12-hour shifts, Day and Night)
Isaac Plain Sump RefurbishmentRPR Technologies logo
Introduction
Acquired by Stanmore Resources in 2015, Isaac Plains Coal Mine began operation in January 2016. Over is 16-year life span it is expected to produce and process over 35 million tonnes of ROM coal. Stanmore holds regular shutdowns to complete maintenance work on the facility. Approximately every 6 months the facility is shut down for a 2-week period to complete this work.

During the most recent shut down period IMATECH were contracted to refurbish the internal coatings on some of the sumps. They in turn contract ACR Technologies to remove the existing Polyurea coating from these sumps with the use of our induction disbonding technology.

Over the 10-day period we were on site, we managed to completely remove the internal coating from 7 sumps. Over 300m2 of Polyurea were removed and recoated within the time period.
Project Work
The coating removal process was divided into 2 sections.

1. Firstly, we used the RPR induction unit to heat up the substrate to approximately 150 degrees. This disbonded the Polyurea from the steel and allowed us to peel it off in large sections.
Isaac Plain Sump Refurbishment
Isaac Plain Sump Refurbishment
By using this method first, we drastically increased the rate of removal of this coating. There was no encapsulation or abrasive needed at this stage. We were able to fully remove the coating before moving onto stage 2.

2. IMATECH then encapsulated the sumps and proceeded to abrasive blast the substrate with 30/60 garnet to the SA 2.5 standard, providing a clean surface before reapplication occurred.
Isaac Plain Sump Refurbishment
Isaac Plain Sump Refurbishment
Conclusions
This project was a complete success. Had IMATECH used traditional coating removal methods, it would have unlikely they could have achieved completion of all 7 sumps. The Polyurea coating was over 2000 microns thick and would have simply taken too long to blast off. Not to mention the amount of garnet that would have been needed to take on the task and the time spend cleaning up after wards.

Using the RPR induction heating units we were able to increase the productivity and provide our client with above expectation results all the while saving them time and money on the project. A great result all over.

Trusted by Australia’s Largest Organisations

BHP logo
BP logo
Caltex logo
WesFarmers logo
Imatech logo
Hydro Tasmania logo
ACR Tech Logo
Australian Coating Removal Technology (ACR Tech) is a different industrial service provider. We challenge the norm to provide safer, smarter and more efficient methods to complete the most complex projects.
CONTACT US
All Content Copyright © 2024 ACR Tech. Website Design Gold Coast by Shared Marketing